As I mentioned in an earlier post, I am adding a turnout in Morrisville at the suggestion of my operating crew. It will provide a second (and longer) runaround/passing track, as well as give access to the south side of the mainline from the eastern approach. In watching operations and trying some moves my self, I agreed the suggestion had merit.
My main concern with making this change though was how long would this take to get completed, and how long until I could schedule the next Op Session? One thing was certain though, nothing would get done unless I actually started the work!
With the required curved turnout in hand, I found I had a little time to get started with this the other night. I knew I would not finish this up in one session, but it seemed best to get started and chip away at the overall work.
I cut the rail with a Dremel tool, then pulled up the flex track. I cleaned up the surface of the Homasote roadbed. As there was no good subroadbed under the area that the new turnout would lead to, I cut out a section of scenery. This was only a piece of foam with some scenic material on top, so it wasn't too tough to remove.
I think the takeaway form this is to break down work that might seem daunting and time consuming into smaller sub projects that can be accomplished in smaller segments of time. It was unlikely I would find the multiple consecutive hours do this work completely in one shot. But tackling it in 3-4 sessions was very do-able.